Call Us/Whatsapp Us: +65 8385 9933 | Email: aman@amanengineering.com.sg for inquiry and free quotation

Eurocode 7 Application: Sizing Permanent ERSS using SS EN 1997-1 Singapore National Annex

Eurocode 7 Application: Sizing Permanent ERSS using SS EN 1997-1 Singapore National Annex

Key Takeaways Permanent ERSS design in Singapore requires more than selecting a wall section. It depends on a clear design basis, reliable ground and groundwater information, correct Eurocode 7 design approaches, and coordinated construction-stage controls. Define the retaining system, design life, design situations, and movement criteria before sizing members. Build characteristic soil and groundwater parameters […]

Eurocode 7 Application: Sizing Permanent ERSS using SS EN 1997-1 Singapore National Annex

Eurocode 7 Application: Sizing Permanent ERSS using SS EN 1997-1 Singapore National Annex

Key Takeaways Permanent ERSS design in Singapore requires more than selecting a wall section. It depends on a clear design basis, reliable ground and groundwater information, correct Eurocode 7 design approaches, and coordinated construction-stage controls. Define the retaining system, design life, design situations, and movement criteria before sizing members. Build characteristic soil and groundwater parameters […]

Permanent Contiguous Bored Pile CBP Walls: Structural Liners and Waterproofing Solutions

Introduction Contiguous bored pile walls achieve permanent retention status when integrated with cast-in-place reinforced concrete facing walls, drainage membranes, and shotcrete applications – converting what begins as a deep excavation support system into a lasting structural element of the building envelope. In Singapore’s dense urban environment, where basement construction routinely pushes below multiple levels and […]

Encroachment & Boundary Constraints: Permanent Tie-Back Anchors vs. Strutting Systems

Encroachment & Boundary Constraints: Permanent Tie-Back Anchors vs. Strutting Systems

Key Takeaways Deep excavations beside property boundaries require the retaining system, construction sequence, approvals, and monitoring plan to be considered together. Permanent tie-back anchors can preserve internal working space but may require rights beyond the site boundary. Strutting keeps support within the site, reducing dependence on neighboring land and easement approvals. Soil, groundwater, excavation depth, […]