A design risk assessment is the structured review in which a project team identifies foreseeable hazards in a design, eliminates or reduces them before construction starts, and records what remains. In Singapore it forms the core of the Design for Safety (DfS) process, and for qualifying projects it is a statutory duty for the developer, designers and contractors. A multidisciplinary engineering team that coordinates the DfS process with the other statutory submissions is the most dependable way to complete it correctly. We offer that coordination through our Design for Safety and Risk Management Facilitator service.
TL;DR
- A design risk assessment identifies hazards at the design stage, rates them against a risk matrix, applies controls and records the residual risk for contractors and future maintenance teams.
- The WSH (Design for Safety) Regulations 2015 apply to qualifying developer projects with a contract sum of $10 million or more that involve development under the Planning Act, and to certain alteration and addition works.
- Developers, designers, contractors, DfS Professionals and building owners each hold defined duties, and the results are kept in the DfS Register.
- Controls follow the hierarchy of controls: elimination, substitution and engineering measures come before administrative measures.
- Assigning the DfS process to a team that already handles authority submissions keeps design risks, drawings and approvals consistent.
Table of Contents
- What a design risk assessment is and why it happens at design stage
- Principles that govern the assessment
- When the regulations apply
- Who is responsible at each stage
- The assessment process step by step
- Communicating residual risk
- The DfS Register
- Our perspective
- Support from Aman Engineering Consultancy
- FAQ
- Sources
What a design risk assessment is and why it happens at design stage
The REDAS Design for Safety Good Practice Guide describes Design for Safety as integrating hazard identification and risk assessment early in design, so that designers and contractors can eliminate or minimise risks across the asset lifecycle. The guide asks teams to consider use and foreseeable misuse, human error and ergonomics, major accident events, emergency response and the minimum justifiable residual risk.
The timing matters. The WSH Council guidelines state that risks should be eliminated from the start of the design, before key decisions are made, because design modifications during construction are additional work that is often not cost-effective. The people considered are not only the construction workforce but also those who maintain, repair, clean, refurbish and eventually demolish the structure.
Principles that govern the assessment
Per the same WSH Council guidelines, three principles apply:
- Eliminate foreseeable design risks where reasonably practicable.
- Where elimination is not possible, reduce risks to as low as reasonably practicable (ALARP), at their source, using collective rather than individual protective measures.
- Manage risks across the structure’s life cycle, from construction through operation and maintenance to demolition.
REDAS adds seven guiding principles for its members: developer commitment, alignment between designers and contractors, early opportunity for hazard identification, asset lifecycle thinking, informed decision making, timely implementation, and design knowledge, capability and communication.
When the regulations apply
The Workplace Safety and Health (Design for Safety) Regulations 2015 apply to construction projects undertaken by a developer in the course of business that involve construction work with a contract sum of $10 million or more and involve development under section 3(1) of the Planning Act. They also apply to projects modifying a permanent structure where a DfS Register has already been kept. REDAS notes that the regulations came into operation on 1 August 2016, that minor amendments were gazetted in 2024, and that the WSH Council published its revised Design for Safety Guidelines in 2022.
A 2025 Hong Kong Legislative Council research paper states that the maximum penalty is a fine of S$50,000 and/or two years’ imprisonment, and that no DfS-specific convictions were recorded in 2020 to 2024. Projects below the thresholds are not subject to the regulations, but the same method remains a sound basis for managing design risk. For a wider view of how permit obligations interact with project scope, see this overview of permit filing requirements for energy storage projects.
Our own guides cover the statutory position in more detail: Design for Safety requirements and the DfS regulations playbook.
Who is responsible at each stage
The WSH Council’s About Design for Safety page assigns the following duties.
| Duty holder | Main responsibility |
|---|---|
| Developer | Works with designers so foreseeable design risks are eliminated or reduced; allocates sufficient time and resources |
| DfS Professional | Convenes DfS review meetings, keeps the DfS Register up to date and reports each risk and its mitigation to the developer |
| Designer | Eliminates or reduces risks through the design, ensures collective protective measures manage residual risks, and makes design, construction and maintenance information available |
| Contractor | Ensures appointed personnel are competent and carries out risk assessments |
| Building owner | Keeps a copy of the DfS Register, communicates foreseeable risks to maintenance and future works, and hands the register to future owners |
A DfS Professional is an individual or organisation delegated by the developer to undertake two of the developer’s duties: convening review meetings and maintaining the register. Under the WSH Council guidelines, the DfS Professional must tell the developer, as soon as possible after each meeting, about each foreseeable risk identified and how it can be eliminated or reduced. The Hong Kong paper notes that Singapore requires both designers and contractors to take part in regular DfS review meetings at key stages such as concept design and pre-construction.
The assessment process step by step
The REDAS guide describes the working method. Each step is where errors tend to enter, so we note what to control.
- Set the risk matrix early. The review team selects a matrix aligned with the developer’s risk tolerance. Changing the matrix midway makes earlier ratings inconsistent.
- Identify hazards. Techniques include checklists, brainstorming, guidewords and lessons-learnt reviews. Hazards should cover construction, operation, maintenance, cleaning and demolition, not construction alone.
- Assess the risk. Each hazard is rated for likelihood and severity against the matrix.
- Select controls. Use the hierarchy of controls and favour higher-level controls where practicable. The NUS-IES Design for Safety Library notes that designers mainly influence elimination, substitution and engineering controls, with administrative controls used to communicate residual risks downstream.
- Reduce to ALARP. Repeat the rating after controls are applied to confirm the residual risk is as low as reasonably practicable.
- Record and communicate. Residual risks and mitigation measures go into the DfS Register and Design Risk Assessment Forms, with drawings and advisory notes where appropriate. The WSH Council guidelines provide a sample form in Annex H.
- Review at each key stage. Hold review meetings at concept design, detailed design and pre-construction, and update the register after each.
In practice, the weakest point is the link between the register and the drawings: a control agreed in a meeting that never reaches a drawing or a specification is not a control. Because we prepare authority submissions and engineering design under one roof, the DfS findings can be checked against the structural, mechanical, electrical and facade drawings as they are issued.
A worked example
Consider a commercial building with a glass facade that needs cleaning and maintenance. The identified hazard is a fall from height during facade cleaning. The first option is elimination, such as designing glazing that can be cleaned from inside. If that is not feasible, an engineering control such as a permanent maintenance access system or anchor points is specified. The residual risk, which is the need for trained personnel to use the system, is recorded in an advisory note and carried into the operation and maintenance manual.

Communicating residual risk
The guidelines recommend advisory notes. Designers must give each person provided with the design its design purpose, the results of calculations, testing or analysis, and the conditions needed to keep the structure free of risks to health and safety. Notes belong in the contract documents for construction, in the O&M manual for maintenance, and in standard operating procedures for occupancy.
The DfS Register
The DfS Register is the collection of documents generated through DfS reviews, and it stays with the structure for its life cycle. According to the WSH Council guidelines, it can include:
- pre-construction information;
- review minutes and design risk assessment forms;
- advisory notes transferred to construction and as-built drawings;
- written notes forming the Maintenance Strategy Report.
Before construction it is kept at the premises of the developer or DfS Professional. During construction it is kept at the worksite, or electronically with document control. On completion it must hold the information needed for safe maintenance, cleaning, additions and alterations, refurbishment or demolition. Our page on risk assessment registers explains how we structure these records.
Our perspective
We treat the design risk assessment as part of the statutory submission sequence, not as a separate paperwork exercise. Hazards identified at concept stage affect structural layout, facade systems, services routing and fire safety, and each of these is submitted to an authority later.
Our approach is single-point statutory coordination with a multidisciplinary PE team, so that a risk recorded in the DfS Register is visible to the engineers who produce the drawings. Where a project also needs BIM, the model can carry the same coordination.
The measure of a good assessment is whether the contractor and the building owner can use the register ten years later. That is the standard we design to.
Aman
Support from Aman Engineering Consultancy
We provide Design for Safety Professional and Risk Management Facilitator works alongside authority approvals, PE endorsements, 3D BIM and project management for developers, construction firms and building owners in Singapore. Developers who need a DfS Professional appointed, review meetings convened and the register maintained can start with our DfS and RMF service page or our main services page.

FAQ
Is a design risk assessment the same as a construction risk assessment?
No. A design risk assessment addresses hazards created by design decisions across the whole life cycle, including maintenance and demolition. A construction risk assessment, carried out by the contractor, addresses hazards in the work methods on site. Our guide to construction risk assessment in Singapore covers the second.
Does every Singapore project need a DfS review?
The regulations apply to qualifying developer projects, chiefly those with construction work of $10 million or more involving Planning Act development, and to works on structures that already have a DfS Register. Confirm the position for a specific project against the regulations or with a DfS Professional.
Who can act as the DfS Professional?
The developer delegates the role to an individual or organisation. The Hong Kong research paper notes the person must be a practicing construction professional with the required DfS training.
What should be in the design risk assessment form?
It records the hazard, the risk rating, the controls selected, the residual risk and the person responsible. The WSH Council guidelines include a sample in Annex H.
Sources
- REDAS Design for Safety Good Practice Guide
- WSH Guidelines on Design for Safety
- WSH Council guidelines (DfS) document
- About Design for Safety, WSH Council
- Workplace Safety and Health (Design for Safety) Regulations 2015
- WSH Guidelines on Design for Safety (Revised 2022) listing
- Hong Kong LegCo research paper on mandatory design requirements
- NUS-IES Design for Safety Library 2026