Cladding in Singapore is regulated through three connected frameworks: the SCDF Fire Code 2023 for material and fire performance, the Building Control regime administered by BCA for plan submissions and periodic façade inspection, and SCDF’s product certification system for regulated composite panels. Developers, contractors and building owners must satisfy all three. Each applies at a different stage: design, installation and the life of the building.
This guide sets out which rules govern cladding, what the Fire Code requires of external walls, which approvals precede installation or alteration, and who is responsible for compliance and inspection once the building is occupied.
TL;DR
- The Fire Code 2023 is the governing document for fire precautions in buildings, and its requirements take precedence where they conflict with a referred code or standard.
- External walls within 1 m of the relevant boundary, or on buildings taller than 15 m, generally must be wholly non-combustible and achieve the required fire resistance.
- Composite panels require a Certificate of Conformity, annual surveillance testing and permanent product marking.
- Cladding work that qualifies as fire-safety work needs SCDF approval before it starts, and structural fixings require a permit and certification through a Qualified Person.
- Owners of buildings over 20 years old must appoint a Competent Person for Periodic Façade Inspection when BCA issues a notice, and must repair defects promptly.
Table of Contents
- The legal and technical framework for cladding
- Fire Code requirements for external-wall cladding
- Certification, testing and marking of composite panels
- Approvals required before installing or altering cladding
- Responsibility, inspection and periodic review
- Consequences of non-compliance
- Assessing cladding on an existing building
- Our perspective
- Support for cladding compliance from Aman Engineering Consultancy
- FAQ
- Sources
The legal and technical framework for cladding
Singapore does not regulate cladding through a single statute. Three instruments carry most of the weight.
The Fire Code 2023. It is SCDF’s Code of Practice for Fire Precautions in Buildings. Its own provisions prevail when they conflict with a code or standard it refers to. Clauses 3.5 (external walls), 3.15 (materials for construction) and Chapter 11 (regulated fire-safety products and materials) are the principal provisions for cladding. For a wider orientation to the code, see our guide to the SCDF Fire Code.
The Building Control framework. The Building Control (Meaning of Exterior Features) Regulations 2021, in force from 1 January 2022, expressly list cladding, curtain walls, siding, tiles, masonry veneer, screens, louvres and fins as exterior features of a building. This definition connects cladding to the façade inspection regime and to building and structural plan submissions.
SCDF’s cladding product regime. Regulated composite panels must be certified, tested and traceable, as described below.
The table summarizes how these instruments divide the subject.
| Concern | Governing instrument | Principal agency |
|---|---|---|
| Combustibility and fire resistance of external walls | Fire Code 2023, clause 3.5 | SCDF |
| Composite panel core materials and test standards | Fire Code 2023, clause 3.15 | SCDF |
| Product certification, surveillance testing and marking | Fire Code 2023, Chapter 11 | SCDF |
| Fire-safety plan approval for cladding work | Fire Safety Act plan approval process | SCDF |
| Structural fixings and load transfer | Structural plan submission | BCA |
| Façade condition over the life of the building | Periodic Façade Inspection | BCA |
Fire Code requirements for external-wall cladding
Non-combustibility and fire resistance
Under clause 3.5 of the Fire Code 2023, an external wall that is within 1 m of the relevant boundary, or that forms part of a building exceeding 15 m in height, must generally be constructed wholly of non-combustible materials. It must also attain the required fire resistance and satisfy the applicable boundary and separation provisions.
Homogeneous cladding must be at least of limited combustibility. The clause states an exception for certain cladding on buildings below 15 m that is at least 1 m from the boundary. Project teams should read the exception in the current text of the clause before relying on it, since the clause was last updated on 3 September 2026.
The practical consequence for design is that the height of the building and its distance from the boundary determine the permitted material palette before any aesthetic decision is made. A façade concept developed without those two parameters frequently has to be redesigned at the submission stage.

Composite panels
Composite panels used as external-wall cladding attract additional conditions. Clause 3.15 requires compliance with clause 3.15.13 and requires the panels to be mounted against a wall with at least one hour of fire resistance.
The same clause allows compliance to be shown in two ways:
- Core material testing. The core meets BS 476 Part 4, BS 476 Part 11, BS 476 Parts 6 and 7 with Class 0 flame spread, or EN 13501-1 Class B.
- Whole-assembly testing. The entire panel assembly complies with NFPA 285.
The route chosen affects which test reports must accompany the submission and what the Registered Inspector will examine on site.
Certification, testing and marking of composite panels
SCDF’s cladding-product regime rests on third-party assurance. According to the SCDF circular on external wall finishes, regulated composite panels need a Certificate of Conformity (CoC) from an accepted certification body. The CoC is based on testing by laboratories accredited by the Singapore Accreditation Council, or recognised under an SAC mutual-recognition arrangement. The circular states that a CoC is valid for five years.
The regime goes beyond a single original test. SCDF has described factory inspections, quality audits and project-site testing as the means of addressing manufacturing inconsistency and undeclared product modification.
Surveillance and project-site testing
The Chapter 11 table requires composite-panel cladding to undergo annual surveillance testing, and additional testing for every project. A project-site test carried out during the surveillance window fulfils that window’s annual test requirement, which allows supply and project testing to be planned together.
Product marking and traceability
Clause 11.8 requires composite panels used as cladding or roofing to carry legible, permanent and conspicuously located marking. The marking states the product brand and model, the CoC reference number, the fire performance and the date of manufacture. Contractors should confirm that deliveries are marked in this way before installation, since panels that cannot be traced to a CoC create difficulties at inspection.
Duties of Qualified Persons and Registered Inspectors
The SCDF circular expects Qualified Persons (QPs) and Registered Inspectors (RIs) to:
- check the test report and the CoC;
- verify that BS or EN tests were performed on the exposed core material where required;
- consider accredited-laboratory testing of samples taken from site where conformity is in doubt.
Approvals required before installing or altering cladding
SCDF fire-safety plan approval
Where cladding work is fire-safety work, SCDF plan approval must be obtained before the work begins, unless an exemption or the minor-alteration lodgement route applies. The plans must be submitted by a QP on behalf of the owner or occupier.
SCDF treats the following as fire-safety works:
- works involving combustible materials;
- changes affecting fire compartments or escape routes;
- relevant additions and alterations.
If the design relies on an alternative solution to the Fire Code, a fire-safety engineer must prepare it and a separate peer reviewer must assess it.
The limits of the minor-alteration exemption
The schedule to Regulation 4(4), in effect from 14 September 2020, excludes work that:
- affects the fire resistance of an element of structure or fire compartmentation;
- poses an additional fire hazard;
- increases floor area;
- involves a change of use beyond the listed ancillary cases;
- involves a conservation project.
A façade replacement that changes the wall build-up, or introduces a combustible insulation layer, will commonly fall outside the exemption.
BCA structural plan submission
For fixings and claddings, BCA’s structural plan submission requirements call for a certification letter from the QP for cladding, together with the main QP and the accredited checker, addressing load-transfer considerations. A permit is required before structural works begin, except for insignificant building works. Our guide to BCA structural submissions covers the sequence in more detail.
BCA building plan submission
The building plan process requires submission before building works start, through a QP who is a registered architect or professional engineer holding a valid practising certificate. The submission must demonstrate compliance with the performance requirements of the Building Control Regulations and with the Approved Document. Further background is available in our articles on building plan submission requirements and the BCA Approved Document.
Suggested sequence for a cladding project
- Establish building height, boundary distances and the fire resistance of the backing wall.
- Select materials against clauses 3.5 and 3.15, and for composite panels, identify the CoC and test route.
- Determine whether the work is fire-safety work and whether any exemption genuinely applies.
- Prepare the building plan, structural plan and fire-safety submissions through the appointed QPs.
- Obtain the QP for cladding’s load-transfer certification for fixings.
- Verify product marking and CoC references on delivery, and arrange project-site testing.
- Complete inspections and obtain the relevant fire-safety certification on completion.
Responsibility, inspection and periodic review
Periodic Façade Inspection
Compliance does not end at completion. Under the Periodic Façade Inspection regime, applicable since January 2022, the owner of a building over 20 years old generally must arrange an inspection every seven years after receiving a notice, subject to stated exceptions. The inspection is intended to detect and address façade deterioration and issues affecting safety.
The owner must appoint a Competent Person (CP) to conduct the inspection and must ensure that identified defects are promptly repaired. The CP may appoint a façade inspector under the CP’s direct supervision and control. Where the CP finds unsafe façade defects, the CP must immediately notify the Commissioner of Building Control and work with the owner on safety measures.

Owners seeking to understand the trigger and the stages can consult our guides on what triggers Periodic Façade Inspection and the owner’s inspection guide.
Responsibility by role
| Party | Principal obligation |
|---|---|
| Owner | Appoint the CP when a PFI notice is received; ensure prompt repair of defects |
| Competent Person | Conduct the PFI; notify the Commissioner of unsafe defects immediately |
| QP and Registered Inspector | Check test reports and CoCs; notify SCDF immediately of suspected non-compliant cladding |
| Contractor and supplier | Supply certified, marked products; support surveillance and site testing |
Consequences of non-compliance
The corrective path differs by the type of failure. A defect found during a PFI must be repaired promptly by the owner, and an unsafe defect is reported to the Commissioner of Building Control without delay.
For fire-safety products, the SCDF circular directs QPs and RIs who suspect non-compliant cladding to notify SCDF immediately. It also states that installing fire-safety products that do not comply with the Fire Code is an offence, absent a lawful excuse. Replacement of non-compliant panels after installation involves redesign, fresh submissions and rework at the owner’s cost, so verification before delivery is the most economical control.
Assessing cladding on an existing building
Owners and asset managers can structure an internal review around five questions:
- Is the building more than 20 years old, or has a PFI notice been received?
- Is a Competent Person appointed, and is the inspection programme documented?
- Are any identified defects recorded with a repair schedule?
- Where composite panels were installed, can the CoC reference, test reports and marking be located?
- Is any planned alteration likely to count as fire-safety work or to affect structural fixings?
A negative or uncertain answer to the fourth question warrants a technical review by a QP, since traceability records are easiest to assemble while project documents remain available.
Our perspective
Cladding failures rarely originate in a single decision. They arise where the façade designer, the fire-safety engineer, the structural engineer and the supplier each satisfy their own part of the requirement and no one reconciles the whole. Boundary distance, building height, backing-wall fire resistance, panel core material and fixing load path are interdependent, and a change to one alters the others.
For that reason we favour single-point statutory coordination. A multidisciplinary team of Professional Engineers working from one coordinated submission programme allows the Fire Code position, the BCA structural certification and the inspection strategy to be settled together rather than in sequence. Our drone inspection capability supports façade assessment on existing buildings, and our stated authority clearance rate of 99% reflects the emphasis we place on transparent requirements at the start of an engagement.
We advise owners and developers to treat the façade as a regulated system across its life: specified correctly at design, verified at delivery and installation, and inspected at the intervals the regime sets.
Aman
Support for cladding compliance from Aman Engineering Consultancy
Aman Engineering Consultancy provides authority approvals, Periodic Façade Inspection, Facade Rectification Works (PFI Stage 2), PE endorsements and Fire Safety Certificate services for developers, contractors and building owners in Singapore. Engagements can cover the submission to the relevant agencies, the inspection of an existing façade, and the rectification works that follow.

Owners who have received a PFI notice can review Periodic Façade Inspection Stage 1, and project teams planning new cladding can start from our authority approvals services or contact us through the Aman Engineering Consultancy website.
FAQ
Must all cladding on a Singapore building be non-combustible?
Not in every case. Under Fire Code clause 3.5, external walls within 1 m of the relevant boundary or on buildings above 15 m generally must be wholly non-combustible. Homogeneous cladding must be at least of limited combustibility, with a stated exception for certain cladding below 15 m and at least 1 m from the boundary. The current clause text should be confirmed for each project.
Do composite panels need certification?
Regulated composite panels require a Certificate of Conformity from an accepted certification body, supported by testing at accredited laboratories. Per the SCDF circular, a CoC is valid for five years. The Fire Code also requires annual surveillance testing, additional project testing and permanent product marking.
Is SCDF approval required to replace cladding?
It depends on whether the work is fire-safety work. Works involving combustible materials, or affecting fire compartments or escape routes, are treated as fire-safety work, and approval must be obtained before they begin unless an exemption applies. A QP submits the plans for the owner or occupier.
When must an owner arrange Periodic Façade Inspection?
Buildings over 20 years old generally must be inspected every seven years after the owner receives a BCA notice, subject to stated exceptions. The owner appoints a Competent Person and ensures that identified defects are promptly repaired.
Who certifies the fixings of cladding?
BCA’s structural plan submission requires the QP for cladding to provide a certification letter, jointly with the main QP and accredited checker, covering load-transfer considerations. A permit is needed before structural works begin, except for insignificant building works.
Sources
- Code of Practice for Fire Precautions in Buildings 2023, SCDF
- Building Control (Meaning of Exterior Features) Regulations 2021
- Fire Code 2023, Clause 3.5 External Wall
- Fire Code 2023, Clause 3.15 Materials for Construction
- SCDF circular on the use of external wall finishes on façades
- Fire Code 2023, Chapter 11 Table 11A
- Fire Code 2023, Clause 11.8 Additional Requirements for Specific Products
- SCDF Plan Approval
- Schedule to Fire Safety (Building and Pipeline Fire Safety) Regulation 4(4)
- BCA Structural Plan Submission
- BCA Building Plan Submission
- BCA Periodic Façade Inspection