Third-Party Review in Singapore: The Accredited Checker System

Independent checker reviewing structural design plans

In Singapore construction, a third-party review is an independent technical check of a structural design by a registered Accredited Checker (AC), carried out before the Building and Construction Authority (BCA) approves the plans. It is mandatory for major building works and for certain structural alterations. It is carried out by a professional engineer with no professional or financial interest in the project. This article sets out when the review applies, who may perform it, what it covers, how it fits into the submission process, and how developers, contractors and building owners should plan for it.

Com
Plan Structural Reviews With Confidence
Aman Engineering Consultancy provides engineering consultancy and statutory submission support for construction projects in Singapore.

Explore engineering services

TL;DR

  • Applications for approval of plans for major building works must include an Accredited Checker’s certificate under the Building Control Act. Underground building works also need a specialist certificate for geotechnical aspects.
  • The checker must be a registered civil or structural professional engineer with at least 10 years of relevant practical experience in Singapore after registration, and must declare independence.
  • The review includes original calculations on key structural elements, and ends with a certificate and an evaluation report submitted to the Commissioner of Building Control.
  • BCA publishes processing times for structural plan submissions with an AC certificate, so the review should be built into the programme before submission.
  • Under CORENET X, the Accredited Checker’s declaration is a precondition for the submission to proceed to agency review.

Table of Contents

What a third-party review means in Singapore

The term is used loosely in the market. In regulatory practice, the formal third-party technical review for building structures is the Accredited Checker system. The checker is not the designer, is not engaged by the contractor to defend a design, and holds no stake in the works. Its function is to provide the Commissioner of Building Control with an independent assessment that the structural design complies with the Building Control Act and its regulations.

The legal basis appears in the Building Control Act, under which applications for approval of plans for major building works are accompanied by an Accredited Checker’s certificate. For underground building works, a specialist Accredited Checker’s certificate for geotechnical aspects is also required, as set out in the BCA summary of the Act’s amendments. The detailed duties of the checker are in the Building Control Regulations, in the version published on Singapore Statutes Online.

Other meanings of the phrase, such as review platforms or vendor due diligence, are unrelated to building control. A developer or owner searching for a third-party review of a structural design should look for an Accredited Checker or an Accredited Checking Organisation (ACO). Our own explanation of the framework is in structural peer review in Singapore.

What a third-party review means in Singapore

When the review is required and when it is voluntary

Mandatory reviews

The review is mandatory in the circumstances the Act and BCA’s submission requirements specify. BCA’s structural plan submission page identifies the following as requiring additional documents:

  1. Submissions requiring an AC certificate, which include the certificate form, the checker’s checklist in the design evaluation report, an evaluation report with the checker’s independent structural analysis and design check calculations, and a standard certification by the checker.
  2. Works on an existing building that materially affect key structural elements, such as strengthening works, which call for the AC’s certificate.
  3. Geotechnical aspects of underground works, which require certification by the specialist Accredited Checker (Geotechnical Aspects) in addition to the Qualified Person for geotechnical works.

Where an alteration does not affect the building’s structural stability or integrity, BCA’s page describes an alternative route: plans endorsed by a Professional Engineer with a prescribed certificate. The classification of a given project into one route or the other is a matter of engineering judgment on the specific works, and it should be settled with the Qualified Person at the outset rather than at submission.

Voluntary reviews

Outside the statutory triggers, an owner, lender or developer may commission an independent technical review of a design, a value engineering proposal or a defect investigation. Such a review does not substitute for the statutory certificate and does not carry the checker’s statutory duties. It is useful where a project team wants an independent opinion on structural adequacy, buildability or cost before committing to construction. The scope, reporting format and independence terms should be agreed in writing at appointment.

Who may perform the review

The Building Control Regulations set the qualifications. A reviewer must be:

  • a professional engineer registered in civil or structural engineering;
  • holding at least 10 years of relevant practical experience in Singapore after registration; and
  • free of any professional or financial interest in the works, confirmed by a declaration of independence.

These requirements are stated in the Building Control Regulations. The same instrument sets the fee for registration or renewal of an Accredited Checker at S$150. BCA publishes registers of individual Accredited Checkers, Accredited Checkers within an ACO, and Specialist Accredited Checkers for geotechnical aspects, which owners can consult to confirm that a proposed reviewer is currently registered.

The independence requirement in practice

Independence is the core of the system. A checker who has contributed to the design, who holds a financial interest in the contractor, or who is engaged by a party with an interest in the outcome cannot give the declaration. Project teams should therefore appoint the checker separately from the design engineer and before the design is frozen, so that comments can be incorporated without disrupting the programme. Our Accredited Checker service page describes how this appointment is typically structured.

What is reviewed and at which stage

The checker’s work is defined by the regulations. The Accredited Checker evaluates, analyses and reviews the structural design in the plans, performs original calculations on key structural elements, and submits a certificate and evaluation report to the Commissioner after completing the review (Building Control Regulations).

Review element What it involves Typical project stage
Design basis Loads, materials, structural system and design codes adopted Before detailed design is finalized
Structural analysis Evaluation of the analysis model and results During detailed design
Original calculations Independent calculations on key structural elements During detailed design
Drawings and details Consistency of structural plans with the calculations Before structural plan submission
Certificate and evaluation report Formal outputs filed for the Commissioner With the structural plan application

The stage column reflects usual project sequencing, not a regulatory timetable. The statutory requirement is that the certificate and evaluation report accompany the application. Where the project involves retaining structures, the duties are discussed in our guide to Accredited Checker for retaining structures.

Documents, comments and notification duties

A review proceeds in a defined sequence.

  1. Appointment and declaration. The checker is appointed and confirms independence.
  2. Submission of design information. The design engineer provides plans, calculations, the design basis and geotechnical information where applicable.
  3. Review and independent calculation. The checker reviews the design and performs original calculations on key elements.
  4. Comments and resolution. The checker issues comments, the design engineer responds or revises, and the cycle repeats until the checker is satisfied.
  5. Certificate and evaluation report. The checker submits these without delay after completing the review, as the regulations require.
  6. Filing with the structural plan application. BCA’s required forms include the certificate form, the checker’s checklist and the evaluation report with the independent calculations.

A further obligation applies throughout. An Accredited Checker or Accredited Checking Organisation must notify the Commissioner of Building Control of known contraventions or non-compliance with the Act in connection with the structural design of plans. This duty is the reason the checker cannot act as an advocate for the design. For a general view of why inspectors report non-compliance in other jurisdictions, see the role of building inspectors in roofing projects.

Because the regulations require the certificate and report “without delay” rather than within a fixed number of days, the duration of the review itself depends on design quality, the number of comment cycles and the responsiveness of the design team.

Timelines at BCA

The published service standards address the BCA processing stage, not the review itself. According to BCA, structural plan applications without an accredited checker’s certification are processed within 7 working days of submission of complete documents. Where the application carries an accredited checker’s certification, processing is within 10 days for a first submission and 14 working days for subsequent submissions (BCA structural plan submission).

BCA processing times by submission type

For programme planning, the review period should be added before these processing times. A realistic schedule sequences the checker’s appointment, one or more comment rounds, certificate issue, and only then the BCA clock. Incomplete documents do not start the clock, so the checklist and evaluation report should be complete before filing. Our structural compliance checklist lists the items most often missing.

How the review connects to CORENET X

CORENET X is the new regulatory approval process for building projects, and it integrates the checker’s role into the digital submission. Under it, relevant project parties, including Accredited Checkers, must make their declarations before the submission can be sent for agency review. Detailed structural submissions may include AC and ACO reports (CORENET X process document).

Two features matter for planning:

  • Phased structural submissions. Under the Regulatory Approval for Building Works (RABW) framework, eligible large projects may make a limited number of part ST submissions, and detailed structural design and calculations, including AC and ACO reports, may be submitted in parts, per the CORENET X refinements page. The checker’s review can therefore be staged with the design.
  • Automated model checking. CORENET X’s Automated Model Checker validates BIM models for quality and regulatory compliance before submission, and agency officers review its results after formal submission (CORENET X process document). A structural model that passes this check reduces avoidable rework.

Further detail is available in our guides to BIM submission standards and the CORENET X submission guide.

Our perspective

We regard the third-party review as a design-quality control that is most effective when the project team engages it early. Where a checker is appointed only after the structural plans are complete, comments arrive when revisions are most expensive. Where the checker is appointed during the design basis stage, the same comments are absorbed into the normal design cycle.

Our multidisciplinary team of Professional Engineers handles statutory submissions across BCA, URA, JTC, HDB, SCDF, PUB and LTA, and we coordinate them through a single point. That coordination matters because a structural comment frequently affects the facade, the mechanical and electrical layout or the fire safety submission. Resolving those interactions in one team shortens the comment cycle.

We also work in BIM, which aligns with the model-based expectations of CORENET X. Our stated authority clearance rate is 99%, and we attribute it to complete documentation and clear requirements at the first submission.

Aman

Planning the review: a practical checklist

Owners, developers and contractors can reduce delay by confirming the following before appointing a checker.

  1. Confirm with the Qualified Person whether the works fall under the AC certificate route or the Professional Engineer endorsement route.
  2. Verify the proposed checker’s current registration on the BCA registers.
  3. Confirm independence in writing: no design role, no financial interest in the works.
  4. Fix the scope: structural superstructure, retaining structures, underground works and geotechnical aspects each have their own requirements.
  5. Agree the information the design team will supply, and the turnaround for comment responses.
  6. Align the review with CORENET X declarations and any phased structural submissions.
  7. Allow for BCA’s published processing times after the certificate is issued.

For wider structural certification obligations, see our structural certification guide for developers, and for the approval sequence overall, streamlining the structural design approval process.

Engaging Aman Engineering Consultancy

Aman Engineering Consultancy provides statutory submissions, authority approvals, PE endorsements, inspections and BIM services for property developers, construction firms and building owners in Singapore. Fees are project-based and quoted per engagement. Teams preparing a structural submission that requires independent review can describe the project through our authority approvals services or the main site.

Com

For existing buildings, our real estate inspection service supports owners who need an independent engineering assessment ahead of alteration or transaction.

FAQ

Is a third-party review the same as an Accredited Checker review?

For structural design in Singapore building control, yes in practice. The Accredited Checker is the independent professional engineer who reviews the design and issues the statutory certificate. Other independent reviews, such as a commissioned peer review of a value engineering proposal, are voluntary and carry no statutory certificate.

Who can act as an Accredited Checker?

A professional engineer registered in civil or structural engineering with at least 10 years of relevant practical experience in Singapore after registration. The person must hold no professional or financial interest in the works and must submit a declaration of independence. Current registrants are listed on BCA’s registers.

How long does the review take?

The regulations set no fixed duration for the review; the certificate and evaluation report must be submitted without delay after the review is completed. BCA then processes an application with a checker’s certification within 10 days for a first submission and 14 working days for subsequent submissions. Review duration depends on design quality and comment cycles.

Does the Accredited Checker report problems to the authority?

Yes. An Accredited Checker or Accredited Checking Organisation must notify the Commissioner of Building Control of known contraventions or non-compliance with the Act in connection with the structural design of plans. Design teams should therefore resolve comments before certification.

Is the Accredited Checker still needed under CORENET X?

Yes. Accredited Checkers are among the project parties who must make declarations before a CORENET X submission can be sent for agency review. Detailed structural submissions may include AC and ACO reports.

Sources